Land Cruiser URJ200 URJ202 GRJ200 VDJ200 - A750F AUTOMATIC TRANSMISSION / TRANSAXLE
VALVE BODY ASSEMBLY - INSPECTION
1. INSPECT SHIFT SOLENOID VALVE SR |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Solenoid Connector (SR) - Solenoid Body (SR) 20°C (68°F) 11 to 15 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) → Shift solenoid valve SR connectorBattery negative (-) → Shift solenoid valve SR bodyValve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
2. INSPECT SHIFT SOLENOID VALVE SLU |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Terminal 1 of shift solenoid valve SLU - terminal 2 20°C (68°F) 5.0 to 5.6 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) with a 21 W bulb → Terminal 2Battery negative (-) → Terminal 1Valve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
3. INSPECT SHIFT SOLENOID VALVE SL2 |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Terminal 1 of shift solenoid valve SL2 - terminal 2 20°C (68°F) 5.0 to 5.6 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) with a 21 W bulb → Terminal 1Battery negative (-) → Terminal 2Valve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
4. INSPECT SHIFT SOLENOID VALVE SLT |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Terminal 1 of shift solenoid valve SLT - terminal 2 20°C (68°F) 5.0 to 5.6 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) with a 21 W bulb → Terminal 2Battery negative (-) → Terminal 1Valve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
5. INSPECT SHIFT SOLENOID VALVE SL1 |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Terminal 1 of shift solenoid valve SL1 - terminal 2 20°C (68°F) 5.0 to 5.6 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) with a 21 W bulb → Terminal 1Battery negative (-) → Terminal 2Valve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
6. INSPECT SHIFT SOLENOID VALVE S1 |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Solenoid Connector (S1) - Solenoid Body (S1) 20°C (68°F) 11 to 15 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) → Shift solenoid valve S1 connectorBattery negative (-) → Shift solenoid valve S1 bodyValve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.
7. INSPECT SHIFT SOLENOID VALVE S2 |

Measure the resistance according to the value(s) in the table below.
- Standard Resistance:
Tester Connection Condition Specified Condition Solenoid Connector (S2) - Solenoid Body (S2) 20°C (68°F) 11 to 15 Ω
Apply 12 V of battery voltage to the shift solenoid valve and check that the valve moves and makes an operating noise.
- OK:
Measurement Condition Specified Condition Battery positive (+) → Shift solenoid valve S2 connectorBattery negative (-) → Shift solenoid valve S2 bodyValve moves and makes an operating noise
If the result is not as specified, replace the solenoid valve.