Combination Meter Installation

Vehicle Interior. Corolla. Zre142 Aze141
Meter Gauge Display. Corolla. Zre142 Aze141

  1. INSTALL COMBINATION METER ASSEMBLY

  2. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY

  3. INSTALL INSTRUMENT PANEL FINISH PANEL END LH

  4. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL LH

Combination Meter -- Installation



1. INSTALL COMBINATION METER ASSEMBLY


    Corolla. Zre142 Aze141
  1. Connect the connector and temporarily install the combination meter assembly.

    NOTICE:
    When installing the combination meter assembly, do not damage the upper instrument panel sub-assembly or combination meter assembly.


    Corolla. Zre142 Aze141
  1. Engage the 2 guides.

    NOTICE:
    1. When installing the combination meter assembly, be careful not to break the guide.
    2. When installing the combination meter assembly, insert the guides securely into the holes on the upper instrument panel sub-assembly.
  1. Install the combination meter assembly with the 2 screws.



2. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY


    Corolla. Zre142 Aze141
  1. Engage the guide, claw and 3 clips, and install the instrument cluster finish panel assembly.

  1. Remove the applied protective tape on the steering column cover.



3. INSTALL INSTRUMENT PANEL FINISH PANEL END LH


    Corolla. Zre142 Aze141
  1. Engage the 2 claws and 2 clips, and then install the instrument panel finish panel end LH.



4. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL LH


    Corolla. Zre142 Aze141
  1. Engage the 3 claws and clip, and then install the lower instrument panel finish panel LH.