  1. INSTALL GENERATOR ASSEMBLY

  2. CONNECT OIL COOLER PIPE ASSEMBLY

  3. CONNECT VANE PUMP ASSEMBLY

  4. INSTALL AIR CLEANER ASSEMBLY

  5. INSTALL AIR CLEANER HOSE ASSEMBLY

  6. INSTALL FRONT FENDER APRON SEAL FRONT RH

  7. INSTALL FAN AND GENERATOR V BELT

  8. INSTALL NO. 1 ENGINE UNDER COVER SUB-ASSEMBLY

  9. INSTALL FRONT FENDER SPLASH SHIELD SUB-ASSEMBLY LH

  10. INSTALL FRONT FENDER SPLASH SHIELD SUB-ASSEMBLY RH

  11. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

  12. INSTALL V-BANK COVER SUB-ASSEMBLY

Generator -- Installation



1. INSTALL GENERATOR ASSEMBLY
  1. Install the stud bolt.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Install the generator with the 3 bolts and nut.

    Torque:
    43 N*m{438 kgf*cm, 32 ft.*lbf}
  1. Connect the harness bracket to the generator with the bolt.

    Torque:
    31 N*m{316 kgf*cm, 23 ft.*lbf}
  1. Connect the generator wire with the nut.

    Torque:
    9.8 N*m{100 kgf*cm, 87 in.*lbf}
  1. Close the terminal cap.

  1. Connect the generator connector.



2. CONNECT OIL COOLER PIPE ASSEMBLY
  1. Connect the oil cooler pipe with the 2 bolts.

    Torque:
    14 N*m{143 kgf*cm, 10 ft.*lbf}


3. CONNECT VANE PUMP ASSEMBLY


Land Cruiser. Urj200, 202 Grj200 Vdj200.3Ur-Fe Battery Charging.Charging System.Generator  Installation
HINT:
Before performing the following procedures, move the spacer until the vane pump can be installed.
Text in Illustration
*1
Spacer
  1. Connect the vane pump to the timing chain cover with the 2 bolts.

    Torque:
    21 N*m{214 kgf*cm, 15 ft.*lbf}


4. INSTALL AIR CLEANER ASSEMBLY
  1. Install the air cleaner with the 3 bolts.

    Torque:
    5.0 N*m{51 kgf*cm, 44 in.*lbf}


5. INSTALL AIR CLEANER HOSE ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.3Ur-Fe Battery Charging.Charging System.Generator  Installation
  1. Install the air cleaner hose so that the protrusion of the air cleaner cap aligns with the groove of the hose as shown in the illustration.

    Text in Illustration
    *1
    Groove
    *2
    Protrusion
  1. Tighten the 2 clamps.

    Torque:
    2.5 N*m{25 kgf*cm, 22 in.*lbf}
  1. Connect the vacuum hose.

  1. Connect the No. 2 ventilation hose.



6. INSTALL FRONT FENDER APRON SEAL FRONT RH
  1. Install the fender apron seal with the 3 clips.



7. INSTALL FAN AND GENERATOR V BELT


    Land Cruiser. Urj200, 202 Grj200 Vdj200.3Ur-Fe Battery Charging.Charging System.Generator  Installation
  1. Set the V belt onto every part.

  1. While turning the belt tensioner counterclockwise, remove the bar.

    Text in Illustration
    *1
    Vane Pump
    *2
    Water Pump
    *3
    No. 1 Idler
    *4
    Fan
    *5
    Generator
    *6
    Belt Tensioner
    *7
    Crankshaft
    *8
    Cooler Compressor
    NOTICE:
    Make sure that the V belt is properly set to each pulley.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.3Ur-Fe Battery Charging.Charging System.Generator  Installation
  1. After installing the belt, check that it fits properly in the ribbed grooves.

    Text in Illustration
    *a
    CORRECT
    *b
    INCORRECT
    HINT:
    Make sure to check by hand that the belt has not slipped out of the grooves on the bottom of the pulley.


8. INSTALL NO. 1 ENGINE UNDER COVER SUB-ASSEMBLY
  1. Install the No. 1 engine under cover with the 10 bolts.

    Torque:
    29 N*m{296 kgf*cm, 21 ft.*lbf}


9. INSTALL FRONT FENDER SPLASH SHIELD SUB-ASSEMBLY LH
  1. Push in the clip to install the front fender splash shield sub-assembly LH.

  1. Install the 3 bolts and screw.



10. INSTALL FRONT FENDER SPLASH SHIELD SUB-ASSEMBLY RH
  1. Push in the clip to install the front fender splash shield sub-assembly RH.

  1. Install the 3 bolts and 2 screws.



11. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).


12. INSTALL V-BANK COVER SUB-ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.3Ur-Fe Battery Charging.Charging System.Generator  Installation
  1. Attach the 2 V-bank cover hooks to the bracket. Then align the 3 V-bank cover grommets with the 3 pins, and press down on the V-bank cover to attach the pins.

    Text in Illustration
    *1
    Bracket
    *2
    Hook
    *3
    Pin
    *4
    Grommet