Рычаг Переключения Передач (Для Моделей С Кузовом Типа Седан) Повторная Сборка. Corolla ZZE150
INSTALL POSITION INDICATOR LIGHT BULB
INSTALL INDICATOR LIGHT WIRE SUB-ASSEMBLY
INSTALL NO. 2 POSITION INDICATOR SLIDE COVER
INSTALL POSITION INDICATOR SLIDE COVER
INSTALL FLOOR SHIFT POSITION INDICATOR HOUSING SUB-ASSEMBLY
Рычаг Переключения Передач (Для Моделей С Кузовом Типа "Седан") -- Повторная Сборка |
1. INSTALL POSITION INDICATOR LIGHT BULB |
Install the cap to the bulb.
Install the bulb to the position indicator light wire socket.
2. INSTALL INDICATOR LIGHT WIRE SUB-ASSEMBLY |
Connect wire harnesses 7 and 14 to the connector as shown in the illustration.
Push in the stopper.
Install the position indicator light wire socket, connector and 3 clamps to the shift lock control unit.
3. INSTALL NO. 2 POSITION INDICATOR SLIDE COVER |
Install the No. 2 position indicator slide cover to the position indicator slide cover.
4. INSTALL POSITION INDICATOR SLIDE COVER |
Install the position indicator slide cover with the No. 2 position indicator to the shift lock control unit.
5. INSTALL FLOOR SHIFT POSITION INDICATOR HOUSING SUB-ASSEMBLY |
Engage the 4 claws and install the floor shift position indicator housing to the shift lock control unit.
- ПРИМЕЧАНИЕ:
- Make sure that the claws are firmly engaged.