Oil Pump Installation

Engine Hybrid System. Land Cruiser. Urj200, 202 Grj200 Vdj200
1Gr-Fe Lubrication. Land Cruiser. Urj200, 202 Grj200 Vdj200

  1. INSTALL TIMING CHAIN COVER SUB-ASSEMBLY

  2. INSTALL FRONT CRANKSHAFT OIL SEAL

  3. INSTALL OIL PAN SUB-ASSEMBLY

  4. INSTALL OIL STRAINER SUB-ASSEMBLY

  5. INSTALL NO. 2 OIL PAN SUB-ASSEMBLY

  6. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY

  7. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY LH

  8. CONNECT FUEL PIPE SUB-ASSEMBLY

  9. INSTALL NO. 2 OIL PIPE

  10. INSTALL NO. 1 OIL PIPE

  11. INSTALL CRANKSHAFT PULLEY

  12. INSTALL OIL FILTER BRACKET

  13. INSTALL OIL FILTER ELEMENT

  14. INSTALL V-RIBBED BELT TENSIONER ASSEMBLY

  15. INSTALL NO. 2 IDLER PULLEY SUB-ASSEMBLY

  16. INSTALL NO. 1 IDLER PULLEY SUB-ASSEMBLY

  17. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY

  18. INSTALL WATER INLET HOUSING

  19. INSTALL ENGINE OIL LEVEL DIPSTICK GUIDE

  20. INSTALL IGNITION COIL ASSEMBLY

  21. INSTALL NO. 2 EMISSION CONTROL VALVE SET (w/ Secondary Air Injection System)

  22. INSTALL NO. 1 EMISSION CONTROL VALVE SET (w/ Secondary Air Injection System)

  23. INSTALL AIR TUBE (w/ Secondary Air Injection System)

  24. INSTALL ENGINE ASSEMBLY

Oil Pump -- Installation



1. INSTALL TIMING CHAIN COVER SUB-ASSEMBLY


  1. Remove any old packing (FIPG material) and be careful not to drop any oil on the contact surfaces of the timing chain cover, cylinder head and cylinder block.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation


    Text in Illustration
    *a
    Cylinder Head and Cylinder Block Side
    *b
    Timing Chain Cover Side
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Clean and degrease
    -
    -
    NOTICE:
    Be sure to clean and degrease the contact surfaces, especially the surfaces indicated in the illustration.
  1. Apply a light coat of engine oil to a new oil pump gasket.

  1. Install the oil pump gasket.



    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply seal packing as shown in the illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Standard seal diameter:
    3.0 to 4.0 mm (0.118 to 0.157 in.)
    Text in Illustration
    *1
    Seal Diameter
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Seal Packing


  1. Apply seal packing to the timing chain cover in a continuous line as shown in the following illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Toyota Genuine Seal Packing 1282B, Three Bond 1282B or equivalent


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation


    Text in Illustration
    *a
    3.0 to 4.0 mm
    *b
    2.0 to 3.0 mm
    *c
    Be sure to apply seal packing
    *d
    Dashed line area (Seal packing: Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent)
    *e
    Alternate long and short dashed line area (Seal packing: Toyota Genuine Seal Packing 1282B, Three Bond 1282B or equivalent)
    *f
    Continuous line area (Seal packing: Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent)
    *g
    Diagonal line area (Seal packing: Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent)
    -
    -
    NOTICE:
    1. When the contact surfaces are wet, wipe them with an oil-free cloth before applying seal packing.
    2. Install the chain cover within 3 minutes and tighten the bolts within 10 minutes after applying seal packing.

    Application Specification:

    Area
    Seal Packing Diameter
    Application Position from Inside Seal Line
    Continuous Line Area
    4.5 mm (0.177 in.) or more
    3.0 to 4.0 mm (0.118 to 0.158 in.)
    Alternate Long and Short Dashed Line Area
    3.5 mm (0.138 in.) or more
    2.0 to 3.0 mm (0.0787 to 0.118 in.)
    Dashed Line Area
    3.5 mm (0.138 in.) or more
    3.0 to 4.0 mm (0.118 to 0.158 in.)
    Diagonal Line Area
    6.0 mm (0.236 in.) or more
    5.0 mm (0.197 in.)


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Align the oil pump drive rotor spline and crankshaft as shown in the illustration. Install the drive rotor and chain cover to the crankshaft.

    Text in Illustration
    *1
    Drive Rotor Spline
    *2
    Crankshaft


  1. Install the timing chain cover with the 26 bolts, labeled A, B, C and D, and the 2 nuts. Tighten the bolts and nuts uniformly in several steps.

    Standard Bolt:
    Item
    Length
    Bolt A
    25 mm (0.984 in.)
    Bolt B
    55 mm (2.17 in.)
    Bolt C
    35 mm (1.38 in.)
    Bolt D
    65 mm (2.56 in.)


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation


    Text in Illustration
    *1
    Nut
    -
    -
    *a
    Area 1
    *b
    Area 2
    *c
    Area 3
    *d
    Area 4
    NOTICE:
    Make sure that there is no oil on the bolt threads.
  1. Tighten the bolts in area 1.

    Torque:
    47 N*m{479 kgf*cm, 35 ft.*lbf}
    HINT:
    Tighten the bolts from bottom to top as shown in the illustration.
  1. Tighten the bolts in area 2.

    Torque:
    23 N*m{235 kgf*cm, 17 ft.*lbf}
  1. Tighten the bolts in area 3.

    Torque:
    23 N*m{235 kgf*cm, 17 ft.*lbf}
    HINT:
    Tighten the bolts and nuts from top to bottom as shown in the illustration.
  1. Tighten the bolts in area 4.

    Torque:
    23 N*m{235 kgf*cm, 17 ft.*lbf}
    NOTICE:
    1. Do not start the engine for at least 2 hours after installation.
    2. Wipe off any seal packing that seeped out around the surfaces of the oil pan and head cover and make sure that there is no seal packing seeping out around the edges.
    HINT:
    Tighten the bolts from bottom to top as shown in the illustration.


2. INSTALL FRONT CRANKSHAFT OIL SEAL


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply MP grease to the lip of a new oil seal.

  1. Using SST and a hammer, tap in the oil seal until its surface is flush with the timing chain cover edge.

    SST
    09226-10010
    NOTICE:
    1. Keep the lip free from foreign matter.
    2. Do not tap the oil seal at an angle.


3. INSTALL OIL PAN SUB-ASSEMBLY
  1. Remove any old packing (FIPG material) and be careful not to drop any oil on the contact surfaces of the cylinder block, rear oil seal retainer and oil pan.

  1. Install 3 new O-rings to the timing chain cover.



    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply seal packing in a continuous line as shown in the illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Standard seal diameter:
    3.0 to 4.0 mm (0.118 to 0.157 in.)
    Text in Illustration
    *1
    Seal Packing
    NOTICE:
    1. Remove any oil from the contact surface.
    2. Install the oil pan within 3 minutes after applying seal packing.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Install the oil pan with the 17 bolts (A, B, C, D and E) and 2 nuts. Tighten the bolts and nuts uniformly in several steps.

    Torque:
    for bolt A, B, C, E, and nut:
    21 N*m{214 kgf*cm, 15 ft.*lbf}
    for bolt D:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
    Standard Bolt:
    Item
    Length
    Bolt A
    60 mm (2.36 in.)
    Bolt B
    45 mm (1.77 in.)
    Bolt C
    25 mm (0.984 in.)
    Bolt D
    16 mm (0.630 in.)
    Bolt E
    70 mm (2.76 in.)
    Text in Illustration
    *1
    Nut
    NOTICE:
    Do not start the engine for at least 2 hours after installation.


4. INSTALL OIL STRAINER SUB-ASSEMBLY
  1. Install the oil strainer with the 2 nuts.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}


5. INSTALL NO. 2 OIL PAN SUB-ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply seal packing in a continuous line as shown in the illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Standard seal diameter:
    3.0 to 4.0 mm (0.118 to 0.157 in.)
    Text in Illustration
    *1
    Seal Packing
    NOTICE:
    1. Remove any oil from the contact surface.
    2. Install the No. 2 oil pan within 3 minutes after applying seal packing.


    Land Cruiser. Urj200, 202 Grj200 Vdj200
  1. Install the No. 2 oil pan with the 10 bolts and 2 nuts. Tighten the bolts and nuts uniformly in several steps.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Nut
    NOTICE:
    1. Tighten the nuts first. After tightening the bolts, check that the nuts and bolts are tightened to the specified torque.
    2. Do not start the engine for at least 2 hours after the installation.


6. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY
  1. Remove any old packing (FIPG material) and be careful not to drop any oil on the contact surfaces of the camshaft housing, timing chain cover and cylinder head cover.



    Land Cruiser. Urj200, 202 Grj200 Vdj200
  1. Apply seal packing as shown in the illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Standard seal diameter:
    2.0 to 3.0 mm (0.0787 to 0.118 in.)
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Seal Packing
    NOTICE:
    1. Remove any oil from the contact surface.
    2. Install the cylinder head cover within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
  1. Install 3 new gaskets.

  1. Install a new gasket to the cylinder head cover.

  1. Install new seal washers to the bolts.



    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Temporarily install the cylinder head cover with the 12 bolts. Tighten the bolts uniformly in several steps.

    Torque:
    for bolt A and D:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
    for bolt B and C:
    21 N*m{214 kgf*cm, 15 ft.*lbf}
    Standard Bolt:
    Item
    Length
    A
    25 mm (0.984 in.)
    B
    35 mm (1.38 in.)
    C
    65 mm (2.56 in.)
    D
    60 mm (2.36 in.)
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt A
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt B
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt C
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt D
    NOTICE:
    Do not start the engine for at least 2 hours after installation.


7. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY LH
  1. Remove any old packing (FIPG material) and be careful not to drop any oil on the contact surfaces of the camshaft housing, timing chain cover and cylinder head cover.



    Land Cruiser. Urj200, 202 Grj200 Vdj200
  1. Apply seal packing as shown in the illustration.

    Seal packing:
    Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
    Standard seal diameter:
    2.0 to 3.0 mm (0.0787 to 0.118 in.)
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Seal Packing
    NOTICE:
    1. Remove any oil from the contact surface.
    2. Install the cylinder head cover within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
  1. Install 3 new gaskets.

  1. Install a new gasket to the cylinder head cover.

  1. Install new seal washers to the bolts.



    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Temporarily install the cylinder head cover with the 12 bolts. Tighten the bolts uniformly in several steps.

    Torque:
    for bolt A and D:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
    for bolt B and C:
    21 N*m{214 kgf*cm, 15 ft.*lbf}
    Standard Bolt:
    Item
    Length
    A
    25 mm (0.984 in.)
    B
    35 mm (1.38 in.)
    C
    70 mm (2.76 in.)
    D
    60 mm (2.36 in.)
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt A
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt B
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt C
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt D
    NOTICE:
    Do not start the engine for at least 2 hours after installation.


8. CONNECT FUEL PIPE SUB-ASSEMBLY
  1. Connect the fuel pipe with the 2 bolts.

    Torque:
    9.0 N*m{92 kgf*cm, 80 in.*lbf}


9. INSTALL NO. 2 OIL PIPE
  1. Make sure that there is no foreign matter on the mesh of the oil control valve filter RH.

    NOTICE:
    Do not touch the mesh when installing the oil control valve filter.
  1. Install a new gasket and temporarily install the oil pipe (on the cylinder head side) with the oil check valve bolt.

  1. Install the oil control valve filter RH to the oil pipe union. Install new gaskets and temporarily install the oil pipe (on the cylinder head cover side).

  1. Tighten the oil pipe union (on the cylinder head side).

    Torque:
    65 N*m{663 kgf*cm, 48 ft.*lbf}
    NOTICE:
    If the link that connects the gaskets is broken, remove the connecting link by using side cutters or a similar tool.
  1. Tighten the oil pipe union (on the cylinder head cover side).

    Torque:
    65 N*m{663 kgf*cm, 48 ft.*lbf}


10. INSTALL NO. 1 OIL PIPE
  1. Make sure that there is no foreign matter on the mesh of the oil control valve filter LH.

    NOTICE:
    Do not touch the mesh when installing the oil control valve filter.
  1. Install a new gasket and temporarily install the oil pipe (on the cylinder head side) with the oil check valve bolt.

  1. Install the oil control valve filter LH to the oil pipe union. Install new gaskets and temporarily install the oil pipe (on the cylinder head cover side).

  1. Tighten the oil pipe union (on the cylinder head side).

    Torque:
    65 N*m{663 kgf*cm, 48 ft.*lbf}
    NOTICE:
    If the link that connects the gaskets is broken, remove the connecting link by using side cutters or a similar tool.
  1. Tighten the oil pipe union (on the cylinder head cover side).

    Torque:
    65 N*m{663 kgf*cm, 48 ft.*lbf}


11. INSTALL CRANKSHAFT PULLEY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Using SST, install the crankshaft pulley with the pulley set bolt.

    SST
    09213-54015(91651-60855)
    09330-00021
    Torque:
    260 N*m{2651 kgf*cm, 192 ft.*lbf}


12. INSTALL OIL FILTER BRACKET
  1. Install the oil filter bracket and a new gasket with the 2 nuts and bolt.

    Torque:
    21 N*m{214 kgf*cm, 15 ft.*lbf}


13. INSTALL OIL FILTER ELEMENT
  1. Clean the inside of the oil filter cap, the threads and O-ring groove.



    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply a light coat of engine oil to a new O-ring for the cap, and then install the O-ring to the groove of the oil filter cap.

    Text in Illustration
    *1
    O-Ring
    *a
    CORRECT
    *b
    INCORRECT
    NOTICE:
    1. Be sure to install the O-ring in the proper location, otherwise oil may leak.
    2. Do not twist the O-ring.
  1. Set a new oil filter element in the oil filter cap.

  1. Remove any dirt or foreign matter from the installation surface of the engine.

  1. Apply a small amount of engine oil to the O-ring again and temporarily install the oil filter cap.

    NOTICE:
    Do not pinch the O-ring for the cap.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Using SST, tighten the oil filter cap.

    SST
    09228-06501
    Torque:
    25 N*m{255 kgf*cm, 18 ft.*lbf}
    Text in Illustration
    *1
    Oil Filter Cap
    *2
    O-Ring
    *3
    Oil Filter Bracket
    *a
    No Gap
    NOTICE:
    After tightening the oil filter cap, make sure that there is no gap and that the O-ring is not protruding.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Apply a small amount of engine oil to a new drain plug O-ring and install the O-ring to the oil filter cap.

    Text in Illustration
    *1
    O-Ring
    NOTICE:
    Before installing the O-ring, remove any dirt or foreign matter from the installation surface of the oil filter cap.
  1. Install the oil filter drain plug.

    Torque:
    13 N*m{133 kgf*cm, 10 ft.*lbf}
    NOTICE:
    Make sure that the O-ring does not get caught between the parts.


14. INSTALL V-RIBBED BELT TENSIONER ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Temporarily install the V-ribbed belt tensioner with the 5 bolts.

    Standard Bolt:
    Item
    Length
    A
    70 mm (2.76 in.)
    B
    33 mm (1.30 in.)
    Text in Illustration
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt A
    Land Cruiser. Urj200, 202 Grj200 Vdj200
    Bolt B
  1. Tighten bolts 1 and 2 in numerical order.

    Torque:
    36 N*m{367 kgf*cm, 27 ft.*lbf}
  1. Tighten the other bolts.

    Torque:
    36 N*m{367 kgf*cm, 27 ft.*lbf}


15. INSTALL NO. 2 IDLER PULLEY SUB-ASSEMBLY
  1. Install the 2 No. 2 idler pulleys with the 2 bolts.

    Torque:
    54 N*m{551 kgf*cm, 40 ft.*lbf}


16. INSTALL NO. 1 IDLER PULLEY SUB-ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Install the No. 1 idler pulley with the bolt.

    Torque:
    54 N*m{551 kgf*cm, 40 ft.*lbf}
    Text in Illustration
    *1
    DOUBLE
    HINT:
    "DOUBLE" is marked on the No. 1 idler pulley to distinguish it from the No. 2 idler pulley.


17. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Install the water by-pass pipe with the 3 bolts.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Connect the 2 hoses.

    Text in Illustration
    *a
    Upward
    *b
    Rearward
    HINT:
    The direction of the hose clamp is indicated in the illustration.


18. INSTALL WATER INLET HOUSING


Land Cruiser. Urj200, 202 Grj200 Vdj200
  1. Install a new O-ring to the water outlet pipe.

  1. Install a new gasket to the water pump.

  1. Apply soapy water to the gasket of the water outlet pipe.

  1. Install the water inlet with the 5 bolts.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Connect the 5 water by-pass hoses.

  1. Connect the oil cooler hose.

  1. Connect the No. 2 oil cooler hose.

  1. Connect the throttle body connector.



19. INSTALL ENGINE OIL LEVEL DIPSTICK GUIDE


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Install a new O-ring to the engine oil level dipstick guide.

    Text in Illustration
    *1
    New O-Ring
  1. Apply a light coat of engine oil to the O-ring.

  1. Push the engine oil level dipstick guide end into the guide hole.

  1. Install the engine oil level dipstick guide with the bolt.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Install the engine oil level dipstick.



20. INSTALL IGNITION COIL ASSEMBLY
  1. Install the 6 ignition coils with the 6 bolts.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Connect the 6 ignition coil connectors.



21. INSTALL NO. 2 EMISSION CONTROL VALVE SET (w/ Secondary Air Injection System)
  1. Install the No. 2 emission control valve set with the 3 nuts.

    Torque:
    21 N*m{214 kgf*cm, 15 ft.*lbf}


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Align the paint mark with the rib and connect the No. 1 air hose.

    Text in Illustration
    *1
    Paint Mark
    *2
    Rib
    *a
    Top
    *b
    LH Side
    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.
  1. Connect the No. 2 emission control valve set connector.



22. INSTALL NO. 1 EMISSION CONTROL VALVE SET (w/ Secondary Air Injection System)
  1. Install the No. 1 emission control valve set with the 3 nuts.

    Torque:
    21 N*m{214 kgf*cm, 15 ft.*lbf}


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. Align the paint mark with the rib and connect the No. 1 air hose.

    Text in Illustration
    *1
    Rib
    *2
    Paint Mark
    *a
    RH Side
    *b
    Top
    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.
  1. Connect the No. 1 emission control valve set connector.



23. INSTALL AIR TUBE (w/ Secondary Air Injection System)


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. for Bank 1 Side:
    Align the paint mark with the projection and connect the air tube assembly to the emission control valve set.

    Text in Illustration
    *1
    Paint Mark
    *a
    Top
    *b
    RH Side
    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.


    Land Cruiser. Urj200, 202 Grj200 Vdj200.1Gr-Fe Lubrication.Lubrication System.Oil Pump  Installation
  1. for Bank 2 Side:
    Align the paint mark with the projection and connect the air tube assembly to the No. 2 emission control valve set.

    Text in Illustration
    *1
    Paint Mark
    *a
    Top
    *b
    LH Side
    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.
  1. Install the 3 bolts.

    Torque:
    10 N*m{102 kgf*cm, 7 ft.*lbf}
  1. Connect the No. 3 air hose.



24. INSTALL ENGINE ASSEMBLY
(Click here)