Land Cruiser URJ200 URJ202 GRJ200 VDJ200 - HEATING / AIR CONDITIONING
AIR CONDITIONING PANEL (w/o Multi-display) - INSTALLATION
- HINT:
1. INSTALL AIR CONDITIONING CONTROL ASSEMBLY |
Connect the connectors.

Insert the radio receiver and attach the 5 claws on its backside.
- NOTICE:
- When inserting the radio receiver, do not press the knobs on it.
2. INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY |

Connect the connectors.
Attach the 7 claws to install the lower center instrument cluster finish panel sub-assembly.
3. INSTALL LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY RH |

Attach the 7 claws to install the lower instrument panel pad sub-assembly.
Install the clip and screw.
4. INSTALL NO. 1 INSTRUMENT PANEL FINISH PANEL CUSHION |

Attach the 7 claws to install the No. 1 instrument panel finish panel cushion.
5. INSTALL LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY LH |

Connect the connectors and attach the 2 clamps.
Attach the 8 claws to install the lower instrument panel pad sub-assembly.
Install the clip and screw.
6. INSTALL NO. 2 INSTRUMENT PANEL FINISH PANEL CUSHION |

Attach the 7 claws to install the No. 2 instrument panel finish panel cushion.
7. INSTALL RADIO RECEIVER ASSEMBLY WITH BRACKET |
w/o Stereo Component Amplifier:
()
w/o Multi-display:
()
8. INSTALL NO. 1 CENTER INSTRUMENT CLUSTER FINISH PANEL |

Connect the connector.
Attach the 10 claws to install the No. 1 center instrument cluster finish panel.
9. INSTALL NO. 4 INSTRUMENT PANEL REGISTER ASSEMBLY |

Connect the connector.
Attach the 6 claws to install the No. 4 instrument panel register.
10. INSTALL NO. 3 INSTRUMENT PANEL REGISTER ASSEMBLY |

Connect the connector.
Attach the 6 claws to install the No. 3 instrument panel register.
11. INSTALL NO. 1 SPEAKER OPENING COVER ASSEMBLY |

Attach the 8 claws to install the opening cover.
12. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- NOTICE:
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected ().