Land Cruiser URJ200 URJ202 GRJ200 VDJ200 - WINCH

WINCH UNIT - REASSEMBLY

1. INSTALL WINCH MOTOR BRUSH SPRING
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the brush spring as shown in the illustration.

2. INSTALL NO. 1 WINCH MOTOR ARMATURE BEARING
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Using a 12 mm socket wrench and press, press in a new bearing.

3. INSTALL NO. 2 WINCH MOTOR ARMATURE BEARING
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Using a 19 mm socket wrench and press, press in a new bearing.

4. INSTALL WINCH MOTOR ARMATURE SUB-ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Apply high temperature grease to the inside of the end frame bushing.

Install the armature to the end frame.

5. INSTALL WINCH MOTOR YOKE SUB-ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Align the alignment marks and install the yoke to the end frame.

6. INSTALL WINCH MOTOR BRUSH HOLDER ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Align the alignment marks and install the brush holder to the yoke.

7. INSTALL WINCH MOTOR BRUSH
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the brush with the bolt.

  • Torque:
  • 3.4 N*m{ 35 kgf*cm, 30 in.*lbf}
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Using a screwdriver, pry the brush spring forward and insert the brush into the holder as shown in the illustration, then remove the screwdriver from the spring.

  • HINT:
  • Use the same procedures to install the 3 remaining brushes.
8. INSTALL WINCH MOTOR O-RING

Install a new O-ring to the yoke.

9. INSTALL WINCH MOTOR COMMUTATOR END FRAME
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the end frame with the 2 bolts.

  • Torque:
  • 7.7 N*m{ 79 kgf*cm, 69 in.*lbf}
10. INSTALL WINCH MOTOR MAGNET SWITCH ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the switch to the motor with the 4 bolts.

  • Torque:
  • 4.9 N*m{ 50 kgf*cm, 43 in.*lbf}
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the wire harness with the 2 washers, 2 spring washers and 2 nuts.

  • Torque:
  • 9.3 N*m{ 95 kgf*cm, 82 in.*lbf}

Connect the connector.

11. INSTALL MAGNET SWITCH WINCH COVER
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the cover with the 4 screws.

  • Torque:
  • 1.5 N*m{ 15 kgf*cm, 13 in.*lbf}
12. INSTALL WINCH ROLLER BRACKET ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the roller bracket with the 4 bolts and 2 nuts.

  • Torque:
  • for bolt A:
  • 21.6 N*m{ 220 kgf*cm, 15 ft.*lbf}
  • for bolt B:
  • 28.4 N*m{ 289 kgf*cm, 20 ft.*lbf}
13. INSTALL NO. 2 WINCH EARTH WIRE
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the winch earth wire with the bolt.

  • Torque:
  • 17.5 N*m{ 178 kgf*cm, 12 ft.*lbf}
14. INSTALL WINCH MOTOR ASSEMBLY
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the winch motor with the 3 bolts.

  • Torque:
  • 15.7 N*m{ 160 kgf*cm, 11 ft.*lbf}
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the winch base with the 8 bolts.

  • Torque:
  • for bolt A:
  • 32.3 N*m{ 329 kgf*cm, 23 ft.*lbf}
  • for bolt B:
  • 58.8 N*m{ 599 kgf*cm, 43 ft.*lbf}
Winch Unit - Reassembly. WINCH. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the member with the 4 bolts.

  • Torque:
  • 21.6 N*m{ 220 kgf*cm, 15 ft.*lbf}