Lexus IS250 IS220d GSE20 ALE20 4GR-FSE ENGINE CONTROL SYSTEM

DESCRIPTION

WIRING DIAGRAM

INSPECTION PROCEDURE

INSPECT ECM (+B, +B1 VOLTAGE)

CHECK HARNESS AND CONNECTOR (ECM - BODY GROUND)

INSPECT ECM (IGSW VOLTAGE)

CHECK FUSE (IGN FUSE)

INSPECT IG2 RELAY

INSPECT ECM (MREL VOLTAGE)

CHECK FUSE (EFI FUSE)

INSPECT INTEGRATION RELAY (EFI MAIN RELAY)

CHECK HARNESS AND CONNECTOR (INTEGRATION RELAY- ECM, INTEGRATION RELAY - BODY GROUND)

SFI SYSTEM - ECM Power Source Circuit

DESCRIPTION

When the engine switch is turned to on, the battery voltage is applied to terminal IGSW of the ECM. The ECM MREL output signal causes a current to flow to the coil, closing the contacts of the EFI MAIN relay and supplying power to terminal +B of the ECM.


If the engine switch is turned to off, the ECM holds the EFI MAIN relay ON for a maximum of 2 seconds to allow for the initial setting of the throttle valve.


When the engine switch is turned on (IG), voltage from the ECM's MREL terminal flows to the integration relay (EFI MAIN relay). This causes the contacts of the integration relay (EFI MAIN relay) to close, which supplies power to terminal +B or +B1 of the ECM.


WIRING DIAGRAM

Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

INSPECTION PROCEDURE

1.INSPECT ECM (+B, +B1 VOLTAGE)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Turn the engine switch on (IG).

Measure the voltage of the A5 and E4 ECM connectors.

  • Standard voltage:
  • Tester ConnectionSpecified Condition
    +B (A5-6) - E1 (E4-7)9 to 14 V
    +B1 (A5-5) - E1 (E4-7)9 to 14 V
OK
Go to step 6
NG
4.CHECK FUSE (IGN FUSE)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Remove the IGN fuse from the cowl side junction block RH.

Measure the resistance of the IGN fuse .

  • Standard resistance:
  • Below 1 Ω

Reinstall the IGN fuse.

NG
REPLACE FUSE
OK
5.INSPECT IG2 RELAY
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Remove the IG2 relay from the engine room J/B and R/B No. 2.

Measure the resistance of the IG2 relay.

  • Standard resistance:
  • Tester ConnectionSpecified Condition
    3 - 510 kΩ or higher
    3 - 5Below 1 Ω
    (when battery voltage applied to terminals 1 and 2)
NG
REPLACE IG2 RELAY
OK
CHECK AND REPAIR SMART ACCESS SYSTEM WITH PUSH-BUTTON START
6.INSPECT ECM (MREL VOLTAGE)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Turn the engine switch on (IG).

Measure the voltage of the A5 and E4 ECM connectors.

  • Standard voltage:
  • Tester ConnectionSpecified Condition
    MREL (A5-13) - E1 (E4-7)9 to 14 V
NG
REPLACE ECM
OK
7.CHECK FUSE (EFI FUSE)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Remove the EFI fuse from the engine room J/B and R/B No. 2.

Measure the resistance of the EFI fuse.

  • Standard resistance:
  • Below 1 Ω

Reinstall the EFI fuse.

NG
REPLACE FUSE
OK
8.INSPECT INTEGRATION RELAY (EFI MAIN RELAY)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Remove the integration relay from the engine room J/B and R/B No. 2.

Measure the resistance of the EFI MAIN relay.

  • Standard resistance:
  • Tester ConnectionSpecified Condition
    2C-1 - 2A-810 kΩ or higher
    Below 1 Ω
    (when battery voltage applied to terminals 2A-6 and 2A-7)
NG
REPLACE INTEGRATION RELAY
OK
9.CHECK HARNESS AND CONNECTOR (INTEGRATION RELAY- ECM, INTEGRATION RELAY - BODY GROUND)
Sfi System - Ecm Power Source Circuit. 4GR-FSE ENGINE CONTROL SYSTEM. Lexus IS250 IS220d GSE20 ALE20

Check the harness and the connectors between the integration relay and the ECM.


Remove the integration relay from the engine room J/B and R/B No. 2.

Disconnect the A5 ECM connector.

Measure the resistance of the wire harness side connectors.

  • Standard resistance (Check for open):
  • Tester ConnectionSpecified Condition
    2A-6 - MREL (A5-13)Below 1 Ω
  • Standard resistance (Check for short):
  • Tester ConnectionSpecified Condition
    2A-6 or MREL (A5-13) - Body ground10 kΩ or higher

Check the harness and the connectors between the integration relay and body ground.


Remove the integration relay from the engine room J/B and R/B No. 2.

Measure the resistance of the wire harness side connector and body ground.

  • Standard resistance (Check for open):
  • Tester ConnectionSpecified condition
    2A-7 - Body groundBelow 1 Ω
NG
REPAIR OR REPLACE HARNESS OR CONNECTOR
OK
CHECK AND REPAIR HARNESS AND CONNECTOR (TERMINAL +B OF ECM - BATTERY POSITIVE TERMINAL)