Combination Meter -- Installation |
- HINT:
- Use the same procedure for RHD and LHD vehicles.
- The procedure listed below is for LHD vehicles.
1. INSTALL COMBINATION METER ASSEMBLY |
![]() |
Connect the connectors.
Install the combination meter assembly with the 4 screws.
2. INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY |
![]() |
Connect the connectors.
Attach the 9 claws to install the No. 2 instrument cluster finish panel sub-assembly.
Attach the 4 claws.
![]() |
3. INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH |
![]() |
Attach the 2 claws to install the No. 2 instrument cluster finish panel garnish.
4. INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH |
![]() |
Attach the 3 claws to install the No. 1 instrument cluster finish panel garnish.
5. INSTALL LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY LH |
for Type A:
Connect the connectors and clamps.
Attach the 11 claws and guide to install the lower instrument panel pad sub-assembly LH.
Install the screw and clip.
for Type B:
Connect the connectors and clamps.
Attach the 8 claws and 2 guides to install the lower instrument panel pad sub-assembly LH.
Install the screw and clip.
6. INSTALL NO. 2 INSTRUMENT PANEL FINISH PANEL CUSHION |
for Type A:
Attach the 4 claws and 3 clips to install the No. 2 instrument panel finish panel cushion.
for Type B:
Attach the 7 claws to install the No. 2 instrument panel finish panel cushion.
7. ENABLE AUTOAWAY/RETURN FUNCTION (for Power Tilt and Power Telescopic Steering Column) |
Restore the autoaway/return function setting to the previous condition by changing the customize parameter (Click here).