Floor Shift Assembly Installation
INSTALL FLOOR SHIFT ASSEMBLY
INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
ADJUST SHIFT LEVER POSITION
INSPECT SHIFT LEVER POSITION
INSTALL FRONT FLOOR HEAT INSULATOR NO.1
INSTALL FRONT EXHAUST PIPE ASSEMBLY
INSTALL NO.2 CONSOLE BOX DUCT
INSTALL CONSOLE BOX
INSTALL CONSOLE BOX REGISTER ASSEMBLY
REMOVE CONSOLE BOX PLATE
INSTALL INSTRUMENT PANEL FINISH PANEL END LH
INSTALL INSTRUMENT PANEL FINISH PANEL END RH
INSTALL CONSOLE UPPER PANEL ASSEMBLY
INSTALL FRONT CONSOLE UPPER PANEL GARNISH
PERFORM INITIALIZATION
Floor Shift Assembly -- Installation |
1. INSTALL FLOOR SHIFT ASSEMBLY |
Install the floor shift assembly with the 4 bolts.
- Torque:
- 8.3 N*m{85 kgf*cm, 73 in.*lbf}
Connect the connector to the floor shift assembly.
2. INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY |
Install the floor shift gear shifting rod sub-assembly with the nut.
- Torque:
- 13 N*m{130 kgf*cm, 9 ft.*lbf}
3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
4. ADJUST SHIFT LEVER POSITION |
Remove the nut and disconnect the shifting rod.
Turn the control shaft lever of the neutral start switch counterclockwise until it stops, and turn it clockwise 2 notches to set it to the N position.
Move the shift lever to the N position and tighten the nut while lightly pushing the lever toward the R position.
- NOTICE:
- Do not push the shift lever too hard.
After adjustment, check that the shift lever moves smoothly and the shift lever and gear operate correctly.
5. INSPECT SHIFT LEVER POSITION |
When shifting from the P to the R position with the engine switch on (IG) and brake pedal depressed, make sure that the shift lever moves smoothly and moves correctly into position.
Start the engine and make sure that the vehicle moves forward when shifting from the N to the D position and moves rearward when shifting to the R position.
If operation cannot be done as specified, inspect the park/neutral position switch assembly and check the shift lever assembly installation condition.
6. INSTALL FRONT FLOOR HEAT INSULATOR NO.1 |
Install the heat insulator No.1 with the 4 nuts.
- Torque:
- 5.4 N*m{55 kgf*cm, 48 in.*lbf}
7. INSTALL FRONT EXHAUST PIPE ASSEMBLY |
(Click here)
8. INSTALL NO.2 CONSOLE BOX DUCT |
Install the console box duct with the 2 clips.
Connect the connector.
Install the console box with the 4 bolts and 2 screws.
10. INSTALL CONSOLE BOX REGISTER ASSEMBLY |
Attach the 4 clips to install the register.
11. REMOVE CONSOLE BOX PLATE |
Connect the connector.
Attach the 4 clips to install the console box.
12. INSTALL INSTRUMENT PANEL FINISH PANEL END LH |
Attach the 4 clips and 3 claws to install the finish panel end.
Install the screw.
13. INSTALL INSTRUMENT PANEL FINISH PANEL END RH |
Attach the 3 clips and 3 claws to install the finish panel end.
Install the screw.
14. INSTALL CONSOLE UPPER PANEL ASSEMBLY |
Connect the connector.
Attach the 9 clips to install the ash receptacle.
Install the shift lever knob and twist it in the direction indicated by the arrow.
15. INSTALL FRONT CONSOLE UPPER PANEL GARNISH |
Attach the claws to install the garnish.
16. PERFORM INITIALIZATION |