INSTALL NO. 1 SIDE DEFROSTER NOZZLE (for Urethane Coating Instrument Panel)
INSTALL NO. 2 SIDE DEFROSTER NOZZLE (for Urethane Coating Instrument Panel)
INSTALL SOLAR SENSOR (for Automatic Air Conditioning System)
INSTALL NO. 1 DEFROSTER NOZZLE GARNISH (for Urethane Coating Instrument Panel)
INSTALL SIDE INSTRUMENT PANEL LH (for Urethane Coating Instrument Panel)
INSTALL SIDE INSTRUMENT PANEL RH (for Urethane Coating Instrument Panel)
INSTALL NO. 1 METER HOOD RETAINER (for Urethane Coating Instrument Panel)
Upper Instrument Panel -- Reassembly |
1. INSTALL NO. 1 INSTRUMENT PANEL CUSHION |
Install a new No. 1 instrument panel cushion as shown in the illustration.
Area Measurement A 0 to 10 mm (0 to 0.394 in.)
![]() |
2. INSTALL NO. 1 SIDE DEFROSTER NOZZLE (for Urethane Coating Instrument Panel) |
Engage the 6 claws to install the No. 1 side defroster nozzle.
![]() |
3. INSTALL NO. 2 SIDE DEFROSTER NOZZLE (for Urethane Coating Instrument Panel) |
Engage the 6 claws to install the No. 2 side defroster nozzle.
![]() |
4. INSTALL SOLAR SENSOR (for Automatic Air Conditioning System) |
Engage the 2 claws to install the solar sensor.
![]() |
5. INSTALL NO. 1 DEFROSTER NOZZLE GARNISH (for Urethane Coating Instrument Panel) |
Engage the 2 clips and 2 claws to install the No. 1 defroster nozzle garnish.
![]() |
6. INSTALL COOLER WIRE (for Automatic Air Conditioning System) |
Engage the clamp.
![]() |
Connect the connector and install the cooler wire.
7. INSTALL NO. 1 INSTRUMENT PANEL REGISTER ASSEMBLY |
Engage the 4 claws to install the No. 1 instrument panel register assembly.
![]() |
8. INSTALL SIDE INSTRUMENT PANEL LH (for Urethane Coating Instrument Panel) |
Engage the 3 claws and 2 guides to install the side instrument panel LH.
![]() |
9. INSTALL NO. 2 INSTRUMENT PANEL REGISTER ASSEMBLY |
Engage the 4 claws to install the No. 2 instrument panel register assembly.
![]() |
10. INSTALL SIDE INSTRUMENT PANEL RH (for Urethane Coating Instrument Panel) |
Engage the 3 claws and 2 guides to install the side instrument panel RH.
![]() |
11. INSTALL FRONT PASSENGER AIRBAG ASSEMBLY |
Engage the 5 hooks.
![]() |
Install the front passenger airbag assembly with the 5 hooks on the instrument panel.
![]() |
Install the 2 screws.
![]() |
12. INSTALL NO. 1 METER HOOD RETAINER (for Urethane Coating Instrument Panel) |
Install the No. 1 meter hood retainer with the 2 screws <B>.
![]() |
13. INSTALL NAVIGATION ANTENNA ASSEMBLY (w/ Navigation System) |
except TMC Made: (COROLLA_ZRE142 RM000002XBS00JX_01_0001.html)
14. INSTALL NO. 4 INSTRUMENT PANEL CUSHION (for TMC Made) |
Install a new No. 4 instrument panel cushion.
![]() |
15. INSTALL NO. 3 INSTRUMENT PANEL CUSHION (for TMC Made) |
Install a new No. 3 instrument panel cushion.
![]() |
16. INSTALL NO. 2 INSTRUMENT PANEL CUSHION (for TMC Made) |
Install a new No. 2 instrument panel cushion.
![]() |
17. INSTALL NO. 2 INSTRUMENT PANEL CUSHION (except TMC Made) |
Install a new No. 2 instrument panel cushion.
![]() |
18. INSTALL NO. 3 HEATER TO REGISTER DUCT |
except Urethane Coating Instrument Panel:
Install the No. 3 heater to register duct with the 3 screws <B>.
for Urethane Coating Instrument Panel:
Install the No. 3 heater to register duct with the 3 screws <B>.
19. INSTALL NO. 1 HEATER TO REGISTER DUCT |
except Urethane Coating Instrument Panel:
Install the No. 1 heater to register duct with the 3 screws <B>.
for Urethane Coating Instrument Panel:
Install the No. 1 heater to register duct with the 3 screws <B>.
20. INSTALL NO. 2 HEATER TO REGISTER DUCT |
Install the No. 2 heater to register duct with the 4 screws <B>.
![]() |
21. INSTALL DEFROSTER NOZZLE ASSEMBLY |
Install the defroster nozzle assembly with the 3 screws <B>.
![]() |