Land Cruiser URJ200 URJ202 GRJ200 VDJ200 - 1GR-FE STARTING
STARTER - INSTALLATION
1. INSTALL FLYWHEEL HOUSING SIDE COVER |
2. INSTALL STARTER ASSEMBLY |
Install the starter with the 2 bolts.
- Torque:
- 37 N*m{ 377 kgf*cm, 27 ft.*lbf}
Connect the starter wire with the nut.
- Torque:
- 9.8 N*m{ 100 kgf*cm, 87 in.*lbf}
Connect the terminal cap.
Connect the starter connector.
Connect the ground wire with the bolt.
- Torque:
- 13 N*m{ 130 kgf*cm, 9 ft.*lbf}
3. INSTALL STARTER COVER |
Install the starter cover with the 3 bolts.
- Torque:
- 12 N*m{ 117 kgf*cm, 8 ft.*lbf}
4. INSTALL EXHAUST MANIFOLD SUB-ASSEMBLY LH |
()
5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- NOTICE:
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected ().