Land Cruiser URJ200 URJ202 GRJ200 VDJ200 - 1UR-FE ENGINE CONTROL

KNOCK SENSOR - INSTALLATION

1. INSTALL KNOCK SENSOR
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the 4 knock sensors with the 4 bolts so that the knock sensors are angled as shown in the illustration.

  • Torque:
  • 20 N*m{ 204 kgf*cm, 15 ft.*lbf}
Text in Illustration
*Afor Bank 2 Sensor 1
*Bfor Bank 1 Sensor 1
*Cfor Bank 2 Sensor 2
*Dfor Bank 1 Sensor 2
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200Front
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200Upper Side
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200Rear

Connect the 4 knock sensor connectors.

2. INSTALL NO. 1 ENGINE COVER
3. INSTALL NO. 2 ENGINE COVER
4. INSTALL SEPARATOR CASE

Install the separator case with the 4 bolts.

  • Torque:
  • 10 N*m{ 102 kgf*cm, 7 ft.*lbf}
5. INSTALL NO. 3 ENGINE COVER
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the No. 3 engine cover.

Text in Illustration
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200Engine Front
  • HINT:
  • Position the No. 3 engine cover so that the arrow mark faces the front of the engine and install it.
6. INSTALL NO. 4 ENGINE COVER
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the No. 4 engine cover.

Text in Illustration
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200Engine Front
  • HINT:
  • Position the No. 4 engine cover so that the arrow mark faces the front of the engine and install it.
7. INSTALL NO. 1 EGR PIPE BRACKET

Install the No. 1 EGR pipe bracket with the 3 bolts.

  • Torque:
  • 21 N*m{ 214 kgf*cm, 15 ft.*lbf}
8. INSTALL NO. 1 WATER OUTLET PIPE

Install the No. 1 water outlet pipe with the 2 bolts.

  • Torque:
  • 10 N*m{ 102 kgf*cm, 7 ft.*lbf}
9. CONNECT NO. 11 WATER BY-PASS HOSE
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Connect the No. 11 water by-pass hose.

Text in Illustration
*1Paint Mark
*aUpper Side
  • HINT:
  • The direction of the hose clamp is indicated in the illustration.
10. CONNECT NO. 8 WATER BY-PASS HOSE
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the No. 8 water by-pass hose.

Text in Illustration
*1Paint Mark
*aUpper Side
*bFront
  • HINT:
When connecting the hose, make sure the paint marks and clips are as shown in the illustration.
The direction of each hose clamp is indicated in the illustration.
11. INSTALL NO. 2 WATER BY-PASS PIPE
Knock Sensor - Installation. 1UR-FE ENGINE CONTROL. Land Cruiser URJ200  URJ202 GRJ200 VDJ200

Install the No. 2 water by-pass pipe with the 2 bolts and connect the hose.

  • Torque:
  • 10 N*m{ 102 kgf*cm, 7 ft.*lbf}
Text in Illustration
*1Paint Mark
*aUpper Side
  • HINT:
When connecting the hose, make sure the paint marks and clips are as shown in the illustration.
The direction of each hose clamp is indicated in the illustration.
12. INSTALL INTAKE MANIFOLD

()